Tanzania: Jacobsen collapse threatens Kinyerezi construction

Tanzania Electric Supply Company (Tanesco) is working with General Electric (GE) to find a way forward for the troubled 185MW expansion of the Kinyerezi I gas power plant. Delays became apparent last year when engineering, procurement and construction (EPC) contractor Jacobsen Elektro told African Energy that only two of the four turbines were on site and a six-to-eight-month delay was expected.

Go to full article

Credit value: 8

African Energy Gulf States Newsletter