Tanzania: Kiliwani North commissioning continues
Issue 325
- 10 Jun 2016
| 1 minute read
Following first gas production from the Kiliwani North field in April, Aminex began commissioning of the gas plant and subsea pipeline on 1 June. The first gas from the field was processed on 2 June and entered the pipeline system connecting the Songo Songo plant with the national pipeline. During the commissioning, gas rates are planned to increase to 30mcf/d while pressuring up the plant and pipeline.