Tanzania: Kiliwani North commissioning continues


Issue 325 - 10 Jun 2016 | 1 minute read

Following first gas production from the Kiliwani North field in April, Aminex began commissioning of the gas plant and subsea pipeline on 1 June. The first gas from the field was processed on 2 June and entered the pipeline system connecting the Songo Songo plant with the national pipeline. During the commissioning, gas rates are planned to increase to 30mcf/d while pressuring up the plant and pipeline.

Tagged with:

Pin Tanzania

Want to read more?

Subscribe to African Energy

View subscription options

Don't have an account?

Register for access to our free content

An account also allows you to view selected free articles, set up news alerts, search our African Energy Live Data power projects database and view project locations on our interactive map

Register