Mauritius: Wärtsilä engines for St Louis rehabilitation


Issue 325 - 10 Jun 2016 | 1 minute read

Finland’s Wärtsilä has won an order to supply a 67MW thermal power plant to replace diesel generating sets at the St Louis power station. The order is for four Wärtsilä 46 engines running on heavy fuel oil. The equipment will be delivered in late 2016, and the plant is scheduled to be operational by September 2017. Burmeister & Wain Scandinavian Contractor is the engineering, procurement and construction contractor for the project. The modernised power station will provide semi-baseload power, including daily starts and stops, to local residents and industries.

Tagged with:

Pin Power

Pin Mauritius

Want to read more?

Subscribe to African Energy

View subscription options

Don't have an account?

Register for access to our free content

An account also allows you to view selected free articles, set up news alerts, search our African Energy Live Data power projects database and view project locations on our interactive map

Register