Liberia: Testing begins at Mount Coffee


Issue 336 - 08 Dec 2016 | 1 minute read

Electrical testing began on the first 22MW unit of the 88MW Mount Coffee hydroelectric power project on 3 December. Mechanical testing has been completed and the unit is expected to be officially commissioned on 15 December. A second turbine is scheduled to be commissioned in February 2017. All four units should be operational by August 2017.