Eranove seeks contractor for new CCGT

Paris-based private equity investor Eranove Group has moved quickly to issue a call for expressions of interest from engineering, procurement and construction (EPC) specialists to develop a new 350MW combined-cycle gas turbine (CCGT) power plant. Eranove’s project fits with government plans to double national generation capacity to 4GW by 2020. The Council of Ministers on 31 August approved a plan for Abidjan’s two established independent power producers, Eranove’s local generation subsidiary Compagnie Ivoirienne de Production d’Electricité (Ciprel) and Globeleq’s Azito Energie, to further expand in the next three years.

Go to full article

Credit value: 6

African Energy Gulf States Newsletter