Cameroon: Bassa starts generating, delays at Logbaba
Issue 297
- 26 Mar 2015
| 1 minute read
London Stock Exchange-listed Victoria Oil and Gas announced on 23 March that its subsidiary Gaz du Cameroun (GDC) had completed the construction of a gas pipeline to Eneo Cameroon’s 20.8MW Bassa power plant and that it was supplying the plant with 4.5mcf/d of gas, allowing the facility to operate at full capacity. The plant comprises 16 generation sets installed by Saudi Arabia’s Altaaqa. However, full operation of a 30MW Eneo power plant at Logbaba, also supplied by gas from GDC and with gensets from Altaaqa, has been put back by one month to April 2015 following shipping delays.