Cameroon: Bassa starts generating, delays at Logbaba


Issue 297 - 26 Mar 2015 | 1 minute read

London Stock Exchange-listed Victoria Oil and Gas announced on 23 March that its subsidiary Gaz du Cameroun (GDC) had completed the construction of a gas pipeline to Eneo Cameroon’s 20.8MW Bassa power plant and that it was supplying the plant with 4.5mcf/d of gas, allowing the facility to operate at full capacity. The plant comprises 16 generation sets installed by Saudi Arabia’s Altaaqa. However, full operation of a 30MW Eneo power plant at Logbaba, also supplied by gas from GDC and with gensets from Altaaqa, has been put back by one month to April 2015 following shipping delays.

Tagged with:

Pin Power

Pin Cameroon

Want to read more?

Subscribe to African Energy

View subscription options

Don't have an account?

Register for access to our free content

An account also allows you to view selected free articles, set up news alerts, search our African Energy Live Data power projects database and view project locations on our interactive map

Register